Water Street River Park

Water Street Timeline August 1, 2016 forward

September 5, 2016

Project team representatives will have a table at Labor Day, and will lead walking tours of the park property

 

Fall 2016

Permitting of floodplain restoration work

 

Fall 2016

FWR to apply for third Ecological Restoration Program grant to help with implementation costs

 

Spring 2017

Construction, scope of which will be dependent on funding available

Possible phasing:

1.  Park area floodplain restoration

2.  Park area recreational amenities

3.  Floodplain restoration downstream of Union Brook